Tuesday, June 8, 2010

Day 35 - 08/06/2010. We have bricks!

They started bricking up the house today and made some good progress considering how wet it is! The bricks look good and I think they will be done by the end of the week. I spoke to our supervisor and he told me that I could go in anytime before the 19th and install my speaker cable and cat5e cable. On the 18th or 19th they plan to install the wall bats and ducted heating and then start on the plaster.

I wasn't going to put any cable in but I figured that I may as well because it will be easier to do it now! I'll add a point to each bedroom and the lounge and playroom. I also spoke to the Telstra Velocity installer and we decided to locate the ONT box on the internal garage wall and also put the phone point in the kitchen.





All the Velocity cables. 1 fibre, 1 coax, 2 cat5e.

No comments: